WHAT'S CHANGING | Energy metering: where J9D3 usually goes wrong

Writer: Rebeka Zubac
Rebeka Zubac
2 hours ago
2 min read

In a building over 2,500 m², NCC clause J9D3 asks for a lot more than a main meter. Air conditioning, lighting, appliance power, central hot water, lifts (where more than one serves the building), on site solar, EV charging and batteries each need their own time of use meter. All of them have to feed one monitoring system where the data can be stored, analysed and reviewed.

What NCC J9D3 requires: over 500 m² gas and electricity meters, over 2,500 m² a meter for each service, one monitoring system
What gets its own meter under J9D3

On paper, that's simple. When it goes wrong, it's usually in one of two ways.

1. No room in the switchboards. Sub meters and current transformers need space. If the boards weren't designed for them, especially the boards serving the air conditioning plant, they end up being retrofitted into live boards later.

2. Meters that aren't connected. On most projects the monitoring system is delivered through the BMS. If the BMS integration and commissioning falls out of everyone's scope, the meters get installed but the data never reaches one screen. The building has the hardware and none of the information.

Where J9D3 goes wrong: no room in the boards, and meters never connected

This matters more from 2027. NCC 2025, which NSW adopts from 1 May 2027, keeps the same metering and adds rules for buildings with an Environmental Management Information System. It has to log key plant data every 5 minutes, allow demand management of solar, batteries, lighting, air conditioning and EV charging, and provide at least two years of data. None of that works without the metering and integration underneath it.

Quick reference (NCC 2022) Over 500 m²: time of use metering for gas and electricity. Over 2,500 m²: separate metering for each service, linked to one monitoring system. Exempt from the separate metering: Class 2 buildings with less than 500 m² of common areas, and meters serving a sole occupancy unit under 2,500 m².

Three questions worth asking at design stage Is there room in the boards for every sub meter? Who owns the BMS integration and commissioning? Who will actually use the data once the building is running?

Three questions to ask at design stage about energy metering

Source: Australian Building Codes Board, NCC 2022 and NCC 2025 Volume One, Part J9